Berlin Brandenburg airport problem of terminal ceiling being too heavy ….. already years late, hugely over budget

Berlin’s long-delayed Brandenburg airport has suffered another setback after structural flaws were found in the terminal roof.  It appears that the ceiling in the terminal building is too heavy. The airport, which was originally due to open in 2010, is still under construction and has run billions of Euros over budget. It was expected to open in 2017 but that could be postponed even further. The local building authority said it had told the construction firm to “immediately stop building works for the area underneath the entire terminal roof of the BER airport” until security checks could be carried out by engineers. The airport’s CEO has left the company. Earlier this year Air Berlin, which is currently running at a loss, reached a settlement with the airport over the delays as it had planned on making BER its main hub airport. The first problems noted were to do with the smoke and fire detection problem. The proposed solution, (which was not surprisingly rejected) was (paraphrased) for 800 low-paid workers armed with cell phones, sitting on camping stools, armed with thermos flasks, who would take up positions throughout the terminal. If anyone smelled smoke or saw a fire, they would alert the airport fire station and direct passengers toward the exits” The airport’s cost, borne by taxpayers, has tripled to €5.4 billion.
.

 

Berlin Brandenburg airport suffers further setback

By Alex McWhirter (Buying Business Travel)

28 Sep 2015

Berlin’s long-delayed Brandenburg airport has suffered another setback after structural flaws were found in the terminal roof.

According to franceinfo.fr the ceiling within the terminal building has been found to be too heavy.

The airport, which was originally due to open in 2010, is still under construction and has run billions of Euros over budget. It was expected to open in 2017 but that could be postponed even further.

The building authority for the Dahme-Spreewald locality said it had told the construction firm to “immediately stop building works for the area underneath the entire terminal roof of the BER airport” until security checks could be carried out by engineers.

German aviation magazine, airportzentrale.de reports that the latest problem has led to Brandenburg’s CEO Karsten Muhlenfeld leaving the company.

In a statement, the airport authority said, “There is no question we are currently in a difficult phase of the project. However we will proceed without compromise.”

Earlier this year Air Berlin, which is currently running at a loss, reached a settlement with the airport over the delays as it had planned on making BER its main hub airport.

http://buyingbusinesstravel.com/news/2824754-berlin-brandenburg-airport-suffers-more-setbacks

.


.

Air Berlin reaches settlement over airport delay

By Tom Newcombe  (Buying Business Travel)
4th Jun 2014

German carrier Air Berlin has agreed an out-of-court settlement with airport operators in its dispute over the delayed opening of the new Berlin Brandenburg airport (BER).

The airport, which was originally due to open in 2010, is still under construction and has run billions of Euros over budget.

Originally planned to be opened in 2010, BER has encountered a series of delays due to poor construction planning, management, execution and corruption

Air Berlin, which is currently running at a loss, had planned on making BER its main hub airport.

“Air Berlin and Berlin Brandenburg GmbH airport operators have agreed an out-of-court settlement in the compensation claim based on the postponement of the opening of Berlin Brandenburg airport BER in 2012,” the airline said in a statement.

“Air Berlin has therefore withdrawn its claim before the regional court of Potsdam. Both parties have agreed not to disclose details of the settlement.”

The planned June 3, 2012 inauguration of the new hub was to replace two smaller airports, Tegel and Schoenefeld.

http://buyingbusinesstravel.com/news/0422584-air-berlin-reaches-settlement-over-airport-delay

.


 

.

How Berlin’s Futuristic Airport Became a $6 Billion Embarrassment

Inside Germany’s profligate (Greek-like!) fiasco called Berlin Brandenburg
July 23, 2015 (Bloomberg)

by Joshua Hammer

Full article contains lots of pictures too   – see link

The inspectors could hardly believe what they were seeing. Summoned from their headquarters near Munich, the team of logistics, safety, and aviation experts had arrived at newly constructed Berlin Brandenburg International Willy Brandt Airport in the fall of 2011 to begin a lengthy series of checks and approvals for the €600 million ($656 million) terminal on the outskirts of the German capital. Expected to open the following June, the airport, billed as Europe’s “most modern,” was intended to handle 27 million passengers a year and crown Berlin as the continent’s 21st century crossroads.

The team of inspectors, known as ORAT, for Operations Readiness and Airport Transfer, brought in a dummy plane and volunteers as test passengers. They examined everything from baggage carousels and security gates to the fire protection system. The last was an especially high priority: None could forget the 1996 fire that roared through Düsseldorf Airport’s passenger terminal, killing 17.

When they simulated a fire, though, the system went haywire. Some alarms failed to activate. Others indicated a fire, but in the wrong part of the terminal. The explanation was buried in the 55-mile tangle of wiring that had been laid, hastily, beneath the floors of the building where ORAT technicians soon discovered high-voltage power lines alongside data and heating cables—a fire hazard in its own right.

That wasn’t all. Smoke evacuation canals designed to suck out smoke and replace it with fresh air failed to do either. In an actual fire, the inspectors determined, the main smoke vent might well implode.

Confronted with the fire system fiasco, Rainer Schwarz, chief executive officer of Flughafen Berlin Brandenburg (FBB), the airport company owned by the city of Berlin, the state of Brandenburg, and the federal government, downplayed it. Schwarz and his staff told the airport’s board of oversight, as well as Stephan Loge, the commissioner of Dahme-Spreewald County, who had the final authority to issue the airport an operating license, that they were working through some issues, but that the situation was under control.

Schwarz also appointed an emergency task force to propose solutions that would allow the airport to open on time. In March 2012 the group submitted its stopgap: Eight hundred low-paid workers armed with cell phones would take up positions throughout the terminal. If anyone smelled smoke or saw a fire, he would alert the airport fire station and direct passengers toward the exits. Never mind that the region’s cell phone networks were notoriously unreliable, or that some students would be stationed near the smoke evacuation channels, where in a fire temperatures could reach 1,000F.

It was, says Martin Delius, “an idiotic plan.” Delius is a physicist and member of Berlin’s parliament who has conducted an extensive investigation of the airport’s troubled infrastructure. “They thought that this would at least eliminate the need for wiring,” he says, “because [the spotters] could see with their own eyes if there is a mass of smoke lower than 6 feet above the ground.”

Schwarz continued to prepare for the opening, and the German public remained oblivious. By April 2012, airport fever was consuming Berlin. Mayor Klaus Wowereit sent out 3,000 invitations for the Hoffest, the annual mayoral ball at the 19th century City Hall, printing the entry tickets on mock boarding cards. Billboards went up, showing a photomontage of the airport’s namesake and famous Cold War leader embracing passengers, with the legend, “Willy Brandt greets the world!”

Preparations continued for an extravagant inaugural. Angela Merkel, the chancellor, was to disembark from a government jet and stroll down a red carpet to the glass-walled terminal, which would have been filled with expensive food and drink. On the night of June 2, in a stunt-like mobilization, thousands of workers would shuttle 600 truckloads of equipment and a fleet of 60-ton aircraft tugs 19 miles down a sealed-off expressway from Berlin-Tegel, Berlin’s main airport, in the northwest corner of the city, and Tegel would shut down forever the same day the new airport came online.

But in the town of Lübben, in what used to be East Germany, Commissioner Loge had his doubts. He and his own staff of building inspectors had spent many hours examining the fire protection system at the Tropical Islands Resort, an indoor paradise set in a former airship hangar in Brandenburg. One of the world’s largest freestanding structures, it draws up to 6,000 warmth-and-beach-deprived Germans a day. “It was far more complicated than the one at Berlin Brandenburg airport, and it worked,” Loge says.On May 7, less than four weeks before the scheduled opening, Loge met with Schwarz for the first time. The airport, Schwarz conceded, would have to open using the army of human fire detectors.

“Professor, let me understand this,” Loge said. “You are talking about having 800 people wearing orange vests, sitting on camping stools, holding thermoses filled with coffee, and shouting into their cell phones, ‘Open the fire door’?” Loge refused the airport an operating license. Schwarz stood up and walked out without another word.The next day, in a hall packed with government officials and journalists, Schwarz sat grimly behind a table with four other officials, including Mayor Wowereit, and announced the unthinkable: The airport wouldn’t open as scheduled. The inaugural bash and overnight move from Tegel were scuttled.

It was merely a prelude to a debacle that is still unfolding. Three years later, Berlin Brandenburg has wrecked careers and joined two other bloated projects—Stuttgart 21, a years-late railway station €2 billion over budget, and an €865 million concert hall in Hamburg—in tarnishing Germany’s reputation for order, efficiency, and engineering mastery.

At the very moment Merkel and her allies are hectoring the Greeks about their profligacy, the airport’s cost, borne by taxpayers, has tripled to €5.4 billion. Two airport company directors (including Schwarz), three technical chiefs, the architects, and dozens if not hundreds of others have been fired or forced to quit, or have left in disgust.

The government spends €16 million per month just to prevent the huge facility from falling into disrepair. According to the most optimistic scenarios, it won’t check in its first passengers until 2017, and sunny pronouncements have long since given way to “catastrophe,” “farce,” and “the building site of horror.” There is a noted German word for the delight some took in the mess, too. [schadenfreude].

In the beginning, Berlin Brandenburg airport was at best an economically unnecessary symbol of unity and growth. In October 1990, when politicians and planners began a search for ways of bridging the city’s long East-West divide, Berlin had three modest-size airports: Tempelhof, famed as the site of the 1948 Berlin Airlift; Schönefeld, opened in 1946, which later became the main airport serving Communist East Germany; and Tegel, a gem of efficiency that opened in 1948. By 1995 about 12 million people flew in and out of the city each year. After years of languishing as a Cold War backwater, Berlin was on the rise. By 2020, passenger totals were projected to reach 22 million.

In 2001, Wowereit sensed an opportunity. A gray-haired extrovert who bears a certain resemblance to the actor Alec Baldwin, “Wowi,” as he’s known, had earned a reputation as both a party animal and a rainmaker. He attracted free-spirited events to the city, such as an international S&M fetish street party, and proudly proclaimed, “I’m gay, and that’s a good thing.” “Is Germany Ready for a Gay Chancellor?” Der Spiegel asked after the Social Democrat’s landslide reelection in 2006. The Berlin Brandenburg Willy Brandt Airport was to be his legacy in the city, while possibly paving the way for national office. (Wowereit declined to be interviewed for this article.)

To design the airport, FBB landed Meinhard von Gerkan, Germany’s most famous architect, a septuagenarian with a mane of white hair who’d made his name at age 30 with the Tegel Airport. The founding partner of Hamburg-based firm von Gerkan, Marg, & Partners, he’s known to squabble publicly with project managers when he feels that his artistic vision has been compromised.

The third key player was Schwarz, who was appointed CEO of the airport management company in 2006. A U.S.-trained economist who’d run Düsseldorf Airport, Schwarz had a reputation as a cost-cutting technocrat—just the man for the job. After considering a half-dozen sites, including a former Russian army base, the airport management team from FBB broke ground in 2006 on a vast plot just a couple of miles from the existing runways at Schönefeld.

The project’s first complications stemmed from Schwarz and Wowereit’s ever-changing ambitions. With construction under way, Schwarz, seizing on increasing forecasts for air traffic (up to 27 million passengers at that point), had von Gerkan add north and south “piers” to the main terminal, turning it from a rectangle into a “U” and dramatically enlarging the floor space. Schwarz also dreamed of making the airport a Dubai-like luxury mall. Airports earn significant money from nonaviation businesses, the FBB boss noted, so why not insert a second level, jammed with shops, boutiques, and food courts? Von Gerkan derided what he called the Vermallung of the airport—its “mallification”—but he capitulated to Schwarz’s demands.

According to Boris Hermel, a TV and radio correspondent who has covered the airport saga from the beginning, and other sources, Wowereit and Schwarz fell hard for an airplane: the Airbus A380, the double-decker, widebody, four-engine jetliner capable of seating 853 people. While no airline indicated it wanted to fly this monstrosity to Berlin, the men called for the walls at one end of the terminal to be ripped out so that an extra-wide gate could be built to accommodate it. “The clients were tripping over each other with requests for changes,” von Gerkan later said.

In his investigation, Delius examined tens of thousands of internal FBB e-mails. “The people responsible for technical oversight were saying, ‘We cannot do this within this amount of time,’ and Schwarz would answer, ‘I don’t care,’ ” he says.

The architecture and engineering teams fought to keep up. As the terminal ballooned from 200,000 to 340,000 square meters (dwarfing Frankfurt’s 240,000 and just shy of Heathrow Terminal 5’s 353,000), they parcelled out the work to seven contractors. That soon grew to 35, and they brought in hundreds of subcontractors, says Delius. Several engineering and electronics companies, led by the German giants Siemens and Bosch, struggled to retain control over the complex fire protection system that included 3,000 fire doors, 65,000 sprinklers, thousands of smoke detectors, a labyrinth of smoke evacuation ducts, and the equivalent of 55 miles of cables.

“Our part, the detection of hot air or smoke … is functioning,” says Thilo Resenhoeft, a Bosch spokesman. “The responsibility for the dysfunction lies with somebody else.” Siemens spokesman Oliver Santen confirms that the company was originally responsible for building the “automated fire protection facility” and “the control unit for fresh-air circulation.” Testing in 2013 “showed the need for reworking part of the system,” he says. Santen declines to attribute responsibility other than to say that Siemens is “responsible for the reconstruction of the fresh-air circulation system.”

Each addition ordered up by Schwarz required shifting passenger flows through the terminal. That meant rebuilding walls, exits, emergency lights, ventilation systems, windows, elevators, and staircases. At one point, in 2009, outside controllers urged Schwarz and his engineering chief to shut down construction for half a year to give the architects and contractors time to coordinate efforts.

Schwarz, Delius says, ignored them. Just months before the scheduled June 2012 opening, the terminal was a mess. Careless workers stepped on and shattered glass being installed by other companies. Heavy equipment rolled across the terminal floor, scratching expensive tiles. Tempers flared; small contractors complained they weren’t getting paid and threatened to walk off the job.

“The number of defects that they’ve found has grown to 150,000”

Following the humiliating announcement in May 2012 that the grand opening was off, the theater of the absurd escalated as executives, board members, and contractors turned on one another. Schwarz presented the board with a list of accusations against von Gerkan and his firm, charging that the architects had misled management with overoptimistic reports on their progress. The architects were fired, along with dozens of other key planners, slowing the project further. “Schwarz lost all their know-how,” says Hermel, the radio journalist. “They were back at Square One.”

Von Gerkan shot back. In a 2013 tell-all book, Black Box BER, he accused Schwarz of resisting all attempts at dialogue. Schwarz “had no concept, only insatiable demands,” von Gerkan wrote, and lived inside “a fairy tale.” That same year, after it became clear that Wowereit’s repeated predictions of an imminent opening were unrealistic, the mayor stepped down as chairman of the board of oversight. (He later resigned as mayor.)

Schwarz was fired days after Wowereit left the board of oversight. He sued for wrongful termination, and in late 2014 a Berlin court ordered the airport owners to pay Schwarz €1.14 million in damages for his dismissal, saying the board of oversight shared responsibility for the fiasco. In an e-mail to Bloomberg Businessweek, Schwarz said he felt vindicated by the court’s decision, concluding, “There is nothing to add.”

In the two years since Schwarz and Wowereit’s dual exit, the owners of the airport have reshuffled the board of oversight and burned through another management team. Schwarz’s successor, a short, stocky official named Hartmut Mehdorn, 72, is a close friend of former German Chancellor Gerhard Schröder. While head of Deutsche Bahn, the German national railway, Mehdorn supervised the construction of Berlin’s Hauptbahnhof, the central train station, in a contentious collaboration with von Gerkan. Hauptbahnhof is considered a German triumph: “If all Americans could compare Berlin’s luxurious central train station today with the grimy, decrepit Penn Station in New York City,” Thomas Friedman wrote in the New York Times in 2008, “they would swear we were the ones who lost World War II.”

Mehdorn came into the Berlin Brandenburg job determined to turn it around. “He is a whirlwind,” says Axel Vogel of the Green Party. After a year of paralysis on the building site, one of Mehdorn’s early moves was to turn on the fountain in front of the deserted terminal to signal that he would get things done. But almost as a mocking counterpoint, the lights in the terminal couldn’t be turned off because of a computer glitch no one could fix, and the electricity bill soared.

Mehdorn squabbled with his engineering chief and antagonized the board of oversight with his ill-conceived schemes to get the airport up and running. At one point he proposed opening just the northern pier. A terrible idea, says Delius: “It was never meant to be opened separately from the rest of the terminal. There were no luggage carousels, no check-in counters, and the only way to reach it would have been to walk across the runway.”

By December 2014 relations between Mehdorn and the board had gotten so bad that the board considered hiring a headhunter to find his replacement, according to Delius and others. Hearing about the plan, Mehdorn quit. After his exit, nobody wanted the job. Mehdorn could not be reached for comment.

In February 2015 the board managed to lure Karsten Mühlenfeld, the well-regarded 51-year-old former chief of engineering at Rolls-Royce Germany. It also hired a former Siemens manager as his technical director. One of the first moves the two made was to yank out and reinstall the miles of cables. Then they turned to the fire prevention system. Smoke now channels upward through chimneys, in accordance with the laws of physics.

The board says construction should be completed by the middle of 2016, to be followed by fresh rounds of testing by ORAT crews. If all goes according to plan, says Mühlenfeld, the airport should begin operations in 2017. Berliners are trying to remain patient as tourism is booming and growth is limited by a lack of flights. “The number of defects that they’ve found has grown to 150,000, including 85,000 serious ones,” says Vogel.

On a Saturday afternoon in July, I board a bus in the Schönefeld parking lot for a two-hour public tour of the deserted airport. The tour leader seems almost to revel in the airport’s cursed history. The project had been a disaster, he says. Still, the terminal building is impressive. We enter the giant structure and walk across floors of light-gray tile, past check-in counters made of artificial walnut. The infamous second level looms above, filled with restaurants and duty-free shops, all done in the same tasteful faux wood. Twin pairs of stainless-steel chimneys rise out of the ceiling. An express train rumbles into the station directly beneath the terminal. Eventually, four trains an hour will whisk passengers to and from central Berlin in 20 minutes. The terminal has a light, spacious feeling, with panoramic sightlines reminiscent of the aesthetics at Berlin Hauptbahnhof.

“You have to say that it is a really cool airport,” Delius says. “The architecture is good. The concept is good. It is very easygoing, easy to navigate. It should please a lot of people—if it ever gets finished.”

http://www.bloomberg.com/news/features/2015-07-23/how-berlin-s-futuristic-airport-became-a-6-billion-embarrassment

.


 

.

Earlier:

Troubled Berlin Brandenburg Airport, due to open in June 2012, Could be shut down in late summer unless € 1.1 billion is raised

Berlin Brandenburg (BER) Airport What Intended to be a huge new airport for Berlin, as Berlin-Schönefeld and Tegel airports Could close. The BER what INITIALLY due to open in June 2012. It had a catalog of problems with fire safety, smoke extraction system, and fresh air supply in the event of fire. The launch has been delayed and delayed …. Last year it photoshoped what it might open this year. Now the airport’s CEO has announced it is Possible That the construction of the airport may need to be shut down this summer, if A Further € 1.1 billion can not be raised. Some € 4.3 trillion has already been spent, but did only lasts till this summer. Extra costs incurred due to the havebeen late opening, as well as the extra construction costs. A decision on how € 1.1 billion can be raised is needed urgently, Perhaps through bank loans, government grants or from Investor. The money has to not only be agreed by Berlin, Brandenburg and the federal government, so but needs approval from the EU Commission. Current total costs amount to € 5.4 billion.  Additional plans suggest additional costs amounting to € 2.19 billion at Extra. Although the airport has yet to open, Officials are planning a possible third runway for Approximately € 1 trillion and other new projects: such as on additional terminal, expanded baggage system and another freight facility.The total additional spending would amount to € 3.2 billion.

https://www.airportwatch.org.uk/2015/03/troubled-berlin-brandenburg-airport-due-to-open-in-june-2012-could-be-shut-down-in-late-summer-unless-e1-1-billion-is-raised/

.

and

Berlin’s Schönefeld airport ‘to stay open’ as Brandenburg airport (at huge expense) not ready till 2015 at the earliest

Berlin’s old Schönefeld airport is likely to remain open as a destination for budget airlines despite a multi-billion airport being built next to it, at Berlin Brandenburg (BER), as the new international hub is too small.  It is the latest in a long line of setbacks to hit the BER, which is over budget and behind time. It will have two runways.  It is expected to open in 2015 at the earliest.  Officially the cost of the airport is €4.3 billion, though initial cost estimates were €1.2 and it could cost up to €6 billion. Despite the huge cost, the airport will only have a capacity of 27 million passengers a year, so its ageing neighbour, Schönefeld, will need to stay open.  The original plan had been for Schönefeld, which caters for budget airlines, to merge with BER.  Keeping Schönefeld in operation would increase capacity by 7.5 million passengers a year and avoid further costs of building a new terminal. Earlier it had been expected that BER  could be partly in use in 2014, with 10 planes per day, but that will not happen.  The airport was initially intended to open in 2010 but the multiple delays have been due to difficulties concerning fire safety, the smoke exhaust systems and construction errors.  Air Berlin is suing BER for damages due to the much delayed opening.  

https://www.airportwatch.org.uk/2014/02/berlins-schonefeld-airport-to-stay-open-as-brandenburg-airport-at-huge-expense-not-ready-till-2015-at-the-earliest/

.


 

Further fire safety problems at Berlin Brandenburg Airport mean it cannot open in October, so delayed till unknown date in 2014

January 8, 2013

Berlin’s Brandenburg airport was initially due to open in June 2012. It has problems with fire safety, smoke extraction system, and fresh air supply in the event of fire. Therefore the opening was put off till October 2013. It has now been announced that the airport will now open on an unknown date in 2014. Based on the previous timetable, construction work was due to be completed by May 2013 to allow a 5-month period for trial operations before the official opening. There may be other technical problems as well, such as on baggage handling. When completed, the airport will take over from the ageing Tegel and Schoenefeld airports. It is expected to be able to eventually handle up to 27 million passengers a year, but this figure has been reduced from the initial figure of 45 million. The cost of the project has risen, from an estimated £1.6 billion to more than £3.2 billion and the latest delays are likely to increase the costs further. A growing chorus of critics is calling for the city’s mayor, Klaus Wowereit, to step down over the matter.

Click here to view full story…

.


 

.

Catalogue of delays and problems for the new Berlin Brandenburg Airport (Willy-Brandt)

Brandenburg (Willy Brandt) airport has become a symbol of how, even for the remarkably technologically successful Germans, things can go horribly wrong. There is currently no opening date set. It has a range of problems, many caused by such complicated and advanced computer systems and technologies, that engineers cannot work out how to fix them. Thousands of light bulbs illuminate the gigantic main terminal and the car park 24 hours per day, which is a massive cost and waste of energy; officials cannot work out how to turn them off as the computer system that’s so sophisticated it’s almost impossible to operate. Every day, an empty commuter train rolls to the unfinished airport over an 8 km stretch to keep the newly-laid tracks from getting rusty – more waste. Several escalators need to be rebuilt because they were too short; and dozen of tiles were already broken before a single airport passenger ever stepped on them. Then there are the fire system problems – with some technology that is so advanced that technicians can’t work out what’s wrong with it.

https://www.airportwatch.org.uk/2013/04/berlin-brandenburg-problems/

.


 

.

Berlin Brandenburg Airport opening date postponed – till March 2013

The new Berlin Brandenburg (Willie Brandt) airport will not now open till March 2013.  It had been due to open in June 2012, and was postponed recently until August 2012.  The problem appears be the fire safety system. The airport can only commence operations with a fully automated fire safety and control system as originally planned, and the interim solution of a partly automated system will not be allowed. This will take until December 2012. In addition, the risk would be too high to move the airport in winter due to adverse weather leading to operational restrictions.  The Managing Director Operations, responsible for the construction of the airport, will have to leave the company. Keeping open the two older Berlin airports that this one will replace will cost about €15 million a month.

https://www.airportwatch.org.uk/2012/05/berlin-airport-opening-postponed/

 

.